Stone and aggregate prices are volatile—and Q2 2026 is shaping up to be expensive. Rising fuel costs, supply chain tightness, and increased demand from commercial projects are pushing material forecasts up 3-8% this quarter, forcing estimators to make smarter bid decisions now.
Crushed stone and aggregate pricing in Q2 2026 is being squeezed by geopolitical and supply chain pressures hitting every commodity market. Crude oil hovering near $100 per barrel as of late March 2026 due to supply disruption fears in the Strait of Hormuz is driving transportation surcharges upward rapidly. For estimators pricing sitework, paving, or masonry scopes right now, the math has changed weekly.
Projects with substantial stone requirements in Q2 demand region-specific forecasts, supplier intelligence, and a bid strategy that locks pricing early while building contingency for material escalation already underway. This article breaks down the cost drivers behind stone prices, provides specific Q2 2026 price forecasts by region and aggregate type, and outlines actionable steps to protect margin when material volatility is standard.
Stone pricing tracks diesel fuel costs, quarry capacity, regional demand, and labor availability—all four factors are pushing prices upward heading into Q2 2026, with fuel surcharges leading. These variables don't move independently; shifts in any one ripple across the entire delivered cost structure.
Diesel fuel is the single largest variable cost in delivered stone pricing. With Brent crude elevated and WTI prices reflecting persistent geopolitical risk, diesel costs ripple through every ton of crushed stone, gravel, and dimensional aggregate reaching your jobsite. Suppliers are passing through fuel surcharges of 2-4% on invoices, updated monthly—sometimes bi-weekly—based on the DOE's weekly diesel price index.
A 20-ton truckload of crushed limestone traveling 30 miles costs $15-30 more per load compared to Q4 2025. For a site development project requiring 5,000 tons of base course aggregate, this adds $3,750-7,500 to your material budget before quarry gate price increases factor in. The math scales directly with tonnage and haul distance.
Request updated pricing from suppliers that explicitly breaks out fuel surcharges from base per-ton costs. Many suppliers provide a base price plus a separate fuel adjustment line item, giving you visibility into what's temporary versus structural cost. If crude oil stabilizes or declines later in 2026, those fuel surcharges could moderate—but build your Q2 bids on current pricing, not speculation about future oil markets.
Quarry output is not keeping pace with demand in several key markets. Major aggregate producers in the Northeast and Mid-Atlantic are reporting lead times of 6-12 weeks for crushed stone and gravel orders, up from the typical 3-4 weeks in stable conditions. A wet winter compounded existing staffing gaps; several quarries operate at 70-85% capacity due to difficulty hiring CDL drivers and heavy equipment operators.
Pennsylvania, New York, and New Jersey markets face higher pricing and extended lead times as a direct result. If your project schedule depends on continuous aggregate deliveries for base course or concrete mix, confirm supplier capacity during preconstruction and lock delivery schedules well before mobilization. A quarry that cannot deliver on time becomes a critical path risk.
Transportation bottlenecks force some suppliers to limit delivery radii or add distance-based surcharges beyond standard service areas. Projects more than 40 miles from the nearest quarry face steeply climbing delivered pricing. Confirm supplier willingness to service your location before locking your estimate.
Aggregate pricing varies dramatically by region, driven by local geology, quarry density, and transportation infrastructure. These forecasts reflect supplier surveys, RSMeans Q2 2026 cost data adjustments, and feedback from estimators actively bidding in these markets.
Midwest (Illinois, Indiana, Ohio): Crushed limestone and gravel prices are up 4-6% compared to Q4 2025. Quarry gate pricing ranges from $14-18 per ton; delivered pricing runs $18-24 per ton depending on haul distance. Illinois commands the higher end due to demand from state bond program infrastructure projects. Indiana and Ohio show slightly softer pricing with better quarry availability and shorter lead times.
Northeast (Pennsylvania, New York, New Jersey): Pricing climbs 5-7% with delivered costs ranging $22-28 per ton for crushed stone. Lead times remain extended due to weather-related production delays earlier in the year. New York metro area projects require confirmation that your supplier meets your schedule; several quarries selectively accept orders and prioritize existing customers only.
Mid-Atlantic (Virginia, Maryland, DC): Budget for 4-6% increases, with delivered pricing of $19-25 per ton. Quarry capacity exceeds Northeast availability, but transportation surcharges hit hard due to metro area congestion. I-495 corridor projects should budget an additional $2-4 per ton for delivery compared to suburban or rural sites.
Southeast (Georgia, Florida, Carolinas): Pricing rises 3-5%, with delivered costs of $16-22 per ton. Florida's limestone supply remains relatively stable, though transportation costs climb from diesel surcharges. Georgia and the Carolinas see steady industrial and warehouse construction demand, keeping quarry utilization high and limiting price competition.
Southwest (Arizona, Nevada, Texas): Expect 4-6% increases with delivered costs of $15-21 per ton. Texas markets tighten due to energy sector construction and border infrastructure projects. Arizona and Nevada offer better availability, but longer haul distances to project sites push delivered pricing higher.
West Coast (California, Oregon, Washington): California pricing climbs 6-8%, with delivered costs of $24-32 per ton—the highest in the continental US. Quarry permitting restrictions, high diesel costs, and strong demand from public infrastructure projects all drive this premium. Oregon and Washington rise 5-7%, with better quarry access but similar transportation cost pressures.
Hawaii: Crushed stone pricing increases 5-7%, with delivered costs of $28-38 per ton depending on island and quarry proximity. Limited quarry capacity and island logistics command pricing well above mainland averages. Hawaii projects require market-specific cost estimating approaches and longer lead time planning.
Dimensional stone—granite, bluestone, limestone—faces similar fuel and transportation pressures as crushed aggregate but with tighter supply constraints. Specialty aggregates like recycled asphalt and engineered fill are experiencing 4-8% price increases, with availability challenges in constrained markets.